7 Eleven Conversion Remodels

  • Full front of house remodel work while stores remain open and in business.  Work performed  mostly at night to not interfere with customers.
  • Erected dust tight barricades to separate the work areas from customer areas.
  • Water filtration system and backflow preventer work at all drink, coffee Slurpee dispensers.
  • Removal of all existing and installation of extensive new 7 Eleven cabinetry/Caseline package.
  • Demolition and replacement of all ceiling lighting fixtures with new LED package.
  • Remove and relocate all equipment including cappuccino machine, coffee brewer, slushie, etc.
  • Install all new graphics package.
  • Paint throughout sales area, common area and restrooms.  Includes painting of all cabinetry.
  • Remove and replace all fixtures and accessories in restrooms.
  • Construct new Gypsum wallboard low walls.
  • New floor tile work.
  • Replace wall panels with FRP and other Wainscott panels.